Drax Carbon Capture Permit Granted for Selby Power Station

The Environment Agency has given Drax a key regulatory win, granting a variation to the environmental permit for its Selby power station so carbon capture can be added to the biomass plant. The decision document was published on 5 August 2026, followed by the Agency’s press release on 14 August 2026, after a final public consultation earlier this summer. (gov.uk) For Eco Current readers, the important point is what this does and does not mean. It is a legal green light for the site to operate under a tighter set of permit conditions if carbon capture is installed; it is not the same thing as the separate development consent already granted for the wider project in January 2024, and it does not settle the wider debate around biomass on its own. (gov.uk)

The process has been long for a reason. Drax first applied on 18 May 2023 and the Environment Agency opened its first consultation from 26 May to 29 June 2023. During that review, the Agency decided the original material did not contain enough information, especially on air emissions, and asked for a more detailed assessment. (assets.publishing.service.gov.uk) A second consultation ran from 4 February to 4 March 2025 after Drax submitted revised emissions work, including possible substances that could form in the capture process. The Agency then consulted again on its draft decision from 27 May to 24 June 2026 before finalising the permit. That slower timetable matters because it shows the regulator did not accept the first version of the case at face value. (gov.uk)

At plant level, the variation covers more than a single capture unit. The final decision document says Drax applied to add a carbon capture activity, solvent treatment, carbon dioxide compression, a new effluent treatment plant linked to the quencher tower, changes to the flue gas layout and abatement, and a hydrogen production activity used to condition captured CO2. The planning project itself is designed around post-combustion capture on up to two existing biomass units. (assets.publishing.service.gov.uk) The carbon dioxide would then leave Selby for permanent geological storage beneath the North Sea. But the Environment Agency is explicit about a key boundary: this permit regulates the operation of the plant itself, not the transport pipeline or offshore storage reservoir. Those later stages fall under other regimes, including the North Sea Transition Authority. For local readers, that legal split is worth keeping in view whenever full project approval is claimed. (gov.uk)

The Agency’s case for approval rests on conditions, and the decision document shows how detailed those conditions are. Before commissioning, Drax must submit methods to demonstrate carbon capture efficiency, including a way to quantify CO2 released during short-duration venting. The document also points to a design basis of capturing 95% of CO2 from the flue gas of Units 1 and 2 during steady-state normal operation, with monitoring and reporting requirements added so performance can be checked rather than assumed. (assets.publishing.service.gov.uk) Other pre-operational checks are just as relevant for neighbours around Selby. The permit requires an updated noise impact assessment based on the final plant design, plans for leak detection and fugitive emissions monitoring covering solvent and hydrogen systems, a CO2 venting assessment, confirmed CO2 monitoring points, and evidence that continuous emissions monitoring equipment meets MCERTS standards. In practice, Drax has won the permit, but it still has to prove the final set-up can meet the rules on the ground before operation starts. (assets.publishing.service.gov.uk)

Public concern did shape the file. In the 2023 consultation stage, the decision document records 10 responses from members of the public and community organisations, including questions about chemical disclosure, nitrosamines, air quality, water pollution and human health. The Agency says it did not accept the original emissions case as sufficient, required further information, and later placed the revised air impact assessment on the public register. (assets.publishing.service.gov.uk) The health and local amenity questions did not disappear in the final round. The UK Health Security Agency asked the Environment Agency to be satisfied that the core modelling was protective across operating scenarios, and the Agency says revised modelling submitted in July 2025 showed emissions of methylethylamine were unlikely to exceed the NDMA environmental assessment level. On noise, the decision document says the capture plant and CO2 compression would not change the current soundscape, although it also notes the existing station noise is calculated to have a significant adverse effect at nearby receptors, which is why an updated assessment before commissioning matters. (assets.publishing.service.gov.uk)

The wider climate argument remains more complicated than the permit notice itself. The Climate Change Committee says engineered removals, including BECCS, need to scale during the 2030s and could deliver 6% of the emissions reduction in its Seventh Carbon Budget pathway by 2040. The same advice also warns that CO2 transport and storage infrastructure must arrive on time and that sustainable biomass supply is a real constraint, with government still working on a common sustainability framework. (theccc.org.uk) That is why critics and supporters are often talking about different questions. The Environment Agency has assessed whether this plant can operate within environmental permit law. It has not ruled on whether burning wood for power is the best use of biomass, and it says feedstock sustainability sits with the Department for Energy Security and Net Zero rather than the permit process. Eco Current readers should treat those as linked but separate tests: local environmental safety, carbon capture performance and biomass sustainability all have to stand up if the project is to earn public confidence. (consult.environment-agency.gov.uk)

So what comes next is not abstract. The most useful questions are now practical ones: the final plant design, the approved noise and fugitive-emissions plans, the method Drax uses to prove capture rates, and how often any venting occurs once the system moves from paper to commissioning. Those are the checkpoints that will show whether this becomes a credible emissions-cutting project or simply a complex promise. (assets.publishing.service.gov.uk) The enforcement side is already clear. The Environment Agency says environmental permits carry strict legal conditions and that its powers include enforcement notices, suspension or revocation of permits, fines and, in serious cases, criminal sanctions. For a project of this scale, that is where the focus now belongs: transparent monitoring, firm regulation and results the public can test. (gov.uk)